Lee County, Illinois Mechanic Lien Lawyer

Unpaid on a Dixon or Lee County project? We help contractors, subcontractors, and suppliers recover payment through mechanic liens, bond claims, and collection litigation.

(847) 432-6900

Last updated: November 2026

Construction Payment Disputes in Lee County

Lee County lies along the Rock River and Interstate 88 in northern Illinois, with Dixon as its county seat. Wind energy projects on farmland, manufacturing and distribution facilities in Dixon, and residential and public work across the county generate work for contractors, subcontractors, and suppliers.

Emalfarb Law LLC serves unpaid contractors, subcontractors, and material suppliers with projects in Lee County from our office in Northbrook. We prepare and record mechanic liens, serve the notices the Illinois Mechanics Lien Act requires, pursue payment bond claims on public work, and litigate lien foreclosure and collection cases in the Lee County circuit court in Dixon.

Wind projects raise two threshold questions before any deadline matters: whether the work is a lienable improvement to real estate at all, and whether the developer holds a leasehold or only an easement.

Lee County Construction Markets We Serve

Lee County's work includes wind energy, industrial, residential, and public segments.

Wind Energy Projects

Wind projects and repowering work involve civil, foundation, crane, and electrical contractors, often on farmland the project company holds under a long-term lease or an easement.

Manufacturing and Distribution

Plant and distribution facilities in and around Dixon involve electrical, mechanical, and structural work under owner-direct contracts and work orders.

Residential Construction and Remodeling

New homes and remodeling in Dixon, Amboy, and the surrounding towns involve builders and trade subcontractors, and the 60-day residential notice often applies to remodeling work.

Schools and Public Work

School districts, the City of Dixon, villages, and the county award building and infrastructure contracts. Public projects generally require a lien on public funds or a payment bond claim.

Where Lee County Mechanic Liens Are Recorded

Dixon is the Lee County seat. Mechanic lien claims affecting Lee County property are recorded with the Lee County Clerk and Recorder, 112 East Second Street, Dixon. Lee County lien foreclosure cases are filed with the Circuit Clerk, ordinarily electronically, in the Circuit Court of Lee County, Fifteenth Judicial Circuit, which sits at the Lee County Courts Building, 309 South Galena Avenue, Dixon.

A wind project can cross many parcels and more than one county. Identify every affected parcel and its county from the recorded documents before choosing the recording office or foreclosure venue.

Lee County

Dixon, Amboy, Ashton, Franklin Grove, Paw Paw, Sublette, Steward, Compton, and other Lee County municipalities.

  • Lien recording: Lee County Clerk and Recorder, 112 E. Second Street (Dixon)
  • Foreclosure court: Circuit Court of Lee County, 15th Judicial Circuit, 309 S. Galena Avenue (Dixon)

Neighboring Counties

Parcels across the county line in Ogle, DeKalb, LaSalle, Bureau, or Whiteside County are recorded and litigated in that county.

Wind Projects on Farmland: Is the Work Lienable?

Wind installations are not automatically lienable improvements to real estate. Courts examine how the installation is attached, how it is adapted to the use of the land, and above all whether the parties intended it to become part of the real estate, including who owns the equipment and who may remove it. In AUI Construction Group, LLC v. Vaessen, 2016 IL App (2d) 160009, the appellate court rejected a mechanics lien involving a wind-energy system because, under the governing agreements, it remained a nonlienable trade fixture. AUI arose from a wind-energy project litigated in the circuit court of Lee County.

The property interest matters as much as the work. A qualifying leasehold may be subject to a lien, as the Illinois Supreme Court recognized in Hacken v. Isenberg, 288 Ill. 589 (1919). An easement is different. Illinois decisions distinguish easements from leaseholds and do not recognize an easement itself as a lienable ownership interest, as in Matanky Realty Group, Inc. v. Katris, 367 Ill. App. 3d 839 (1st Dist. 2006), and AUI. The agreement's substance, not simply its label, must be examined. Because lien rights on a wind project may be limited, a claimant should also evaluate its contract claim and any payment bond or guaranty at the start of the job.

Sample Deadline Walkthrough: Lee County Wind Project

A civil subcontractor completes access road and foundation work on a privately owned wind project in Lee County on March 6, 2026. The project company holds its rights in the farmland under recorded agreements with the landowners. The general contractor stops paying, and the subcontractor has no contract with the project company or the landowners. Assume the work is a qualifying lienable improvement and the project company holds a true leasehold, not an easement.

Section 24 notice: Within 90 days after completion, by June 4, 2026, under 770 ILCS 60/24, on the owner of record or another recipient authorized by the statute, and on the lending agency, if known. Section 24 contains exceptions, including a qualifying sworn statement, but serving the notice is the protective course.

Record the lien claim or commence suit: To preserve the lien against other creditors, encumbrancers, and purchasers, by July 6, 2026, four months after completion under Sections 7 and 28, record a sufficient verified claim with the Lee County Clerk and Recorder or commence a lien-enforcement action in the Lee County circuit court.

File the foreclosure suit: Within two years after completion under Sections 9 and 28, by March 6, 2028, in the Lee County circuit court, unless suit was already commenced. A properly served Section 34 demand can require suit, or an answer in a pending suit, within 30 days after receipt, or the lien is forfeited.

Illinois law generally extends a statutory deadline that falls on a weekend or statutory holiday to the next business day under 5 ILCS 70/1.11, but our practice is to complete the required step earlier rather than depend on the final available day. These examples assume the stated date is the legally operative completion or final-furnishing date and that no shorter demand deadline or other special circumstance applies. A subcontractor proceeding under Section 28 must also observe that section's 10-day period after notice before filing suit, so serving notice and filing suit are not interchangeable steps. The 10-day period applies before filing suit, not before recording the lien claim. On a leased-land project, serve both the fee owner and the project company. Timely notices and filings cannot cure a nonlienable trade fixture or a nonlienable easement interest. Confirm your own deadlines with counsel before relying on them.

How We Handle Lee County Payment Disputes

We confirm the parcel's county and owner of record from the county records before preparing a lien claim for a Lee County project.

We serve the Section 24, Section 21(c), and other notices that apply to your role, and we track the 90-day, four-month, two-year, and Section 34 deadlines.

We order title work and identify every necessary party before filing a foreclosure.

We evaluate the lien, any payment bond, the contract claim, and any personal guaranty together, and we file suit promptly when a demand letter will not resolve the matter.

Lee County Communities We Serve

Dixon
Amboy
Ashton
Franklin Grove
Paw Paw
Sublette
Steward
Compton
West Brooklyn
Harmon
Nelson
Lee

Frequently Asked Questions, Lee County Construction Law

Dixon is the Lee County seat. Mechanic lien claims affecting Lee County property are recorded with the Lee County Clerk and Recorder, 112 East Second Street, Dixon. Under Section 7 of the Illinois Mechanics Lien Act, 770 ILCS 60/7, recording a sufficient verified claim in the correct county, or commencing suit, within four months after completion preserves the lien against creditors, encumbrancers, and purchasers; for subcontractors, that requirement operates through Sections 7 and 28. Section 7 requires a description sufficiently correct to identify the property, and in practice an accurate legal description and property index number are the prudent way to meet it. Confirm the owner of record and the county from the county records and title information before recording. The practical consequence is that you should obtain the deed or title commitment before drafting the lien, not after.

A lien foreclosure on Lee County property is filed in the Circuit Court of Lee County, Fifteenth Judicial Circuit, Lee County Courts Building, 309 South Galena Avenue, Dixon. Under Section 9 of the Illinois Mechanics Lien Act, 770 ILCS 60/9, suit generally must be filed, or a counterclaim asserted, within two years after completion of the contract or the extra or additional work, and a Section 34 demand can shorten that period to 30 days after receipt. Section 11 requires the claimant to join the owner, the contractor, persons in the contract chain between the claimant and the owner, persons who have asserted or may assert Mechanics Lien Act liens, and persons against whose property interests the claimant asserts its claim. Not every person with any conceivable interest is invariably mandatory, but the statutory categories are. The practical consequence is that a title search and contract-chain investigation should be completed before the complaint is drafted, so every necessary party is named and the case is not delayed by amendments.

Possibly, but not automatically. Under Section 1 of the Illinois Mechanics Lien Act, 770 ILCS 60/1, a lien requires a qualifying improvement to real estate under a contract with the owner or with someone the owner authorized or knowingly permitted to contract. Two threshold problems arise on wind projects. First, the installation may be a removable trade fixture, not a lienable improvement. In AUI Construction Group, LLC v. Vaessen, 2016 IL App (2d) 160009, the appellate court rejected a lien involving a wind-energy system on that ground, emphasizing the developer's retained ownership and removal rights. Second, the project company's interest matters. A qualifying leasehold may be subject to a lien, but Illinois decisions distinguish easements from leaseholds and do not treat an easement itself as a lienable ownership interest. Reaching the landowner's fee interest requires facts showing the landowner authorized or knowingly permitted a qualifying improvement. The practical consequence is that you should obtain the deed, the recorded memorandum, and the complete underlying agreement before relying on lien rights, and consider other security, such as a payment bond or guaranty, at the start of the job.

A subcontractor or material supplier without a direct contract with the owner generally must serve written notice of its claim within 90 days after completing its own work, including qualifying extra or additional work. The requirement appears in Section 24 of the Illinois Mechanics Lien Act, 770 ILCS 60/24. The notice must go to the owner of record or an authorized statutory recipient and to the lending agency, if known, and must state the amount due or to become due. Since January 1, 2025, Section 24 permits service by registered or certified mail, return receipt requested, by a nationally recognized delivery company with tracking, or by personal service. Section 24 dispenses with the owner notice when a qualifying sworn statement already identifies the claimant and the amount due, though protection may be limited to the amount stated. The practical consequence is that the notice should be served well before the 90th day, not on it.

A private mechanic lien generally cannot attach to public real estate, so Illinois provides two other remedies. Section 23 of the Illinois Mechanics Lien Act, 770 ILCS 60/23, permits a lien on eligible public funds owed to the contractor. For a local public body, the sworn notice goes to its clerk or secretary before the funds are paid out, a copy goes to the contractor at once, and the claimant must file the statutory accounting action within 90 days after serving the notice and deliver a copy of the complaint within 10 days after filing. The Public Construction Bond Act, 30 ILCS 550, generally requires a payment bond on public work over $150,000 as of 2026. A bond claimant must file a verified notice within 180 days after its last furnishing, send the contractor a copy within 10 days, and sue within one year after last furnishing. Projects for the City of Dixon, Lee County, and local school and park districts fall within these rules. The practical consequence is that you should request the payment bond at the start of the project.

You generally have 30 days to act. Under Section 34 of the Illinois Mechanics Lien Act, 770 ILCS 60/34, the owner or any interested person may serve a written demand requiring the lien claimant to commence suit to enforce the lien. A properly prepared demand contains the statutory warning in at least 10-point boldface type and is served by registered or certified mail, return receipt requested, or by personal service. If the claimant does not commence suit, or answer asserting the lien in a pending suit, within 30 days after receipt, the lien is forfeited. The demand does not automatically extinguish the contract claim against the party responsible for payment, but the security of the lien is lost. Owners often serve these demands before a sale or refinancing. The practical consequence is that a Section 34 demand needs immediate legal review, because service on your agent or attorney can start the period.

Related Construction Law Services

Not sure if you still have lien rights?

Tell us your last work date and project details. We will confirm your deadlines and recommend the strongest available remedy.

All inquiries answered within 1 business day.